ST-CIAL-01•Worksite / Runway
Taxiway Charlie Extension
Active
Associated ProjectCargo Apron & Rapid Exit Taxiway Extension
Location LandmarkAirside Sector 3, Cochin Airport
Supervisor In-ChargeT. P. Haridas+91 98951 77200
Active Activities3 Work Streams
Site Notes
Airside runway subgrade preparation under airport security control.
Activities at this Location
Earthmoving and civil works based at Taxiway Charlie Extension
Excavation
63% Airside Foundation Excavation
Completed: 38,000 Cu.mTarget: 60,000 Cu.m
Transportation
60% Airport Sub-base Aggregate Haulage
Completed: 3,100 TripsTarget: 5,200 Trips
Compaction
62% Runway Base Vibratory Compaction
Completed: 28,000 Sq.mTarget: 45,000 Sq.m
Deployed Fleet & Machinery
No machinery currently assigned to this site in today's roster.