Project Details

Operations Dashboard

Cargo Apron & Rapid Exit Taxiway Extension

Active•₹ 3.20 Cr
Project ManagerRajesh Annangadan
Contract Timeline2026-02-01 – 2026-09-30
Active Worksites2 Locations
Contractual Streams3 Scope Items
Contract Value

₹ 3.20 Cr

Cochin International Airport Ltd (CIAL)

Overall Progress63%

3 of 3 activities near completion

Haulage & Trips

0

0 Delivered

Machine Operating Hours

0.0 hrs

3 Heavy Plant Units Logged

Scope of Earthmoving Activities

Excavation

Airside Foundation Excavation

Location: Taxiway Charlie Extension

63%
Executed: 38,000 Cu.mTarget: 60,000 Cu.m
Allocated Units:
Transportation

Airport Sub-base Aggregate Haulage

Location: Perumbavoor Borrow Quarry ➔ Taxiway Charlie Extension

60%
Executed: 3,100 TripsTarget: 5,200 Trips
Allocated Units:
Compaction

Runway Base Vibratory Compaction

Location: Taxiway Charlie Extension

62%
Executed: 28,000 Sq.mTarget: 45,000 Sq.m
Allocated Units:

Operational Worksites

Site NameTypeLocationSite SupervisorStatus
Taxiway Charlie ExtensionWorksite / RunwayAirside Sector 3, Cochin AirportT. P. HaridasActive
Perumbavoor Borrow QuarrySource / QuarryPerumbavoor East, ErnakulamSanthosh UrangattActive