Cargo Apron & Rapid Exit Taxiway Extension
Active•₹ 3.20 Cr
Project ManagerRajesh Annangadan
Contract Timeline2026-02-01 – 2026-09-30
Active Worksites2 Locations
Contractual Streams3 Scope Items
Contract Value
₹ 3.20 Cr
Cochin International Airport Ltd (CIAL)
Overall Progress63%
3 of 3 activities near completion
Haulage & Trips
0
0 Delivered
Machine Operating Hours
0.0 hrs
3 Heavy Plant Units Logged
Scope of Earthmoving Activities
Excavation
63% Airside Foundation Excavation
Location: Taxiway Charlie Extension
Executed: 38,000 Cu.mTarget: 60,000 Cu.m
Allocated Units:
Transportation
60% Airport Sub-base Aggregate Haulage
Location: Perumbavoor Borrow Quarry ➔ Taxiway Charlie Extension
Executed: 3,100 TripsTarget: 5,200 Trips
Allocated Units:
Compaction
62% Runway Base Vibratory Compaction
Location: Taxiway Charlie Extension
Executed: 28,000 Sq.mTarget: 45,000 Sq.m
Allocated Units:
Operational Worksites
| Site Name | Type | Location | Site Supervisor | Status |
|---|---|---|---|---|
| Taxiway Charlie Extension | Worksite / Runway | Airside Sector 3, Cochin Airport | T. P. Haridas | Active |
| Perumbavoor Borrow Quarry | Source / Quarry | Perumbavoor East, Ernakulam | Santhosh Urangatt | Active |