NH-66 Hill Cutting & Four-Laning Bypass
Active•₹ 4.50 Cr
Project ManagerSajeesh OM
Contract Timeline2026-01-15 – 2026-12-31
Active Worksites3 Locations
Contractual Streams5 Scope Items
Contract Value
₹ 4.50 Cr
Larsen & Toubro (L&T) Heavy Civil
Overall Progress57%
3 of 5 activities near completion
Haulage & Trips
2
1 Delivered(1 In Transit)
Machine Operating Hours
11.5 hrs
5 Heavy Plant Units Logged
Scope of Earthmoving Activities
Breaking
61% Hard Rock Hydraulic Breaking
Location: Sector 7 Hill Cutting Pit
Executed: 29,400 Cu.mTarget: 48,000 Cu.m
Allocated Units:
Excavation
67% Mass Earth Excavation & Bench Dressing
Location: Sector 7 Hill Cutting Pit
Executed: 84,000 Cu.mTarget: 1,25,000 Cu.m
Allocated Units:
Transportation
64% Muck & Aggregate Haulage to Embankment
Location: Sector 7 Hill Cutting Pit ➔ South Embankment Reclamation
Executed: 6,120 TripsTarget: 9,500 Trips
Allocated Units:
Leveling
49% Sub-grade Leveling & Cross-fall Forming
Location: South Embankment Reclamation
Executed: 42,000 Sq.mTarget: 85,000 Sq.m
Allocated Units:
Compaction
46% Aggregate Layer Soil Compaction
Location: South Embankment Reclamation
Executed: 39,500 Sq.mTarget: 85,000 Sq.m
Allocated Units:
Operational Worksites
| Site Name | Type | Location | Site Supervisor | Status |
|---|---|---|---|---|
| Sector 7 Hill Cutting Pit | Source / Quarry | Ramanattukara Bypass, Kozhikode | Santhosh Urangatt | Active |
| South Embankment Reclamation | Fill / Disposal | Feroke Lowland Sector, Kozhikode | V. M. Latheef | Active |
| Central Crushing Yard | Processing / Crusher | Pantheerankavu Industrial Hub | K. Sukumaran | Active |